Friday’s Construction Update: September 11, 2020



Friday, September 11, 2020 at the Hall of Fame Aquatic Complex

Construction continues and everyday they are making progress.

Friday, September 11, saw the Dive well getting its concrete pour.


The crew
continues to work tirelessly and looks to be right on schedule.

Rain or Sun, they just keep working…….

Cubic Yards of Concrete:  546

Trucks:  61

Hours:  10

More Construction Shots